Tabor Sewer Repair Project: Upcoming work through August


Construction is continuing on Environmental Services’ Tabor Sewer Repair Project.
This project in its entirety is scheduled to be completed by fall 2017.

There will be construction phases at each location:
video inspection
saw-cutting
spot repairs
manhole replacement
pipe installation
lateral connection from each building to the curb
stormwater inlet replacement
temporary paving
final trench paving and restoration

CONSTRUCTION SCHEDULE
The map posted at Tabor Sewer Project shows the anticipated construction schedule through August, 2017. Work on each phase will take a few weeks to complete and there will be periods of inactivity between construction phases.

The contractor will apply temporary pavement after completing pipe installation in all work areas. Final trench paving and restoration will occur later as scheduling and weather allows.

Please be aware that our contractor will be taking advantage of dry and warmer weather as it happens for both asphalt and concrete final trench paving. There will be short notice given and street closures for up to a week where concrete is poured.

Areas on the map, marked in gray, are currently not on the schedule or are not completed.
The construction schedules are subject to change due to underground conditions, weather, traffic impacts, subcontractor schedules and availability of materials.

FOR MORE INFORMATION
With questions or comments, please contact Joe Annett or 503-823-2934.
Thank you,
Joe Annett
Community Outreach and Information
City of Portland Environmental Services
1120 SW 5th Ave, Room 1000
Portland, Oregon 97204

2 comments on “Tabor Sewer Repair Project: Upcoming work through August

Leave a Comment

You may use these HTML tags and attributes:
<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong>

*

− 3 = 3